Projects

IMC Building Enhancement - Bologna Centrale Station

  • Location - Country: Italy - Bologna
  • Client: Italferr S.p.A.
  • Time frame: 2016-2017
  • Works amount: € 10'491'066.69
  • Scope of works: Drafting of graphic drawings, descriptive and calculation reports about Detailed Project of enhancement of IMC (Current Maintenance System) Bologna Centrale
  •   Download project document
Share:   

Trenitalia had to accomplish works, in order to improve maintenance system productivity in Bologna Centrale. SGAI S.r.l. dealt with the following aspects: - expansion design of existing building, through extension in prefabricated structures of ALE remittance of 140 m and TD remittance of 150 m. - seismic adjustment of existing building, through structural reinforcements; - hydraulic design of expanding building; - hydraulic design of ALE garage-side platform and under-floor washing platforms in the square in front of building (Bologna side); - structural elements design to support equipment inside the expanding building; - metal frame design for supporting equipment inside the expanding building; Design documents were developed with BIM methodology.